Capsule house site storage should be treated as a controlled project stage whenever a delivered unit cannot move directly into installation. The record should identify the exact unit, arrival condition, approved storage location, responsible custodian, protection measures, inspection triggers, access history and release condition.

This article does not provide a universal storage method. Product support, lifting, covering, ventilation, weather protection and allowable storage conditions must come from order-specific supplier information, the contract and qualified site professionals.

Close the Receiving Record First

Before the carrier leaves or responsibility changes, identify the unit and packages and record visible condition in the agreed receiving process. Separate pre-existing observations from damage or changes that occur during later storage.

Use the capsule house receiving inspection to create a dated arrival baseline. Link photographs and exceptions to stable unit and package identifiers.

Approve the Storage Location

Confirm that the responsible parties have reviewed access, ground or support conditions, slope, drainage, exposure, overhead and underground constraints, security and the future route to installation. Do not move the unit to an improvised location merely because the planned area is occupied.

The storage position should not block emergency access, site operations or later lifting. Any temporary supports, restraints or protective systems require project-specific definition and authorization.

Site Storage Protection Record

ControlRecordCheck
IdentityOrder, unit, packages and receiving recordIs the stored scope traceable?
LocationPlan reference, access and responsible custodianWas the location accepted?
ProtectionApproved support, restraint, covering and security referencesDoes the record match instructions?
MonitoringScheduled and event-based checks, findings and actionsAre changes escalated?
ReleaseFinal condition, open items and installation handoffIs the next team informed?

Control Access and Changes

Name the custodian and record authorized entry, movement, removal of packaging or protective work. Prevent site teams from using the unit for unplanned storage or removing components without an instruction. Preserve keys, documents and loose items through a controlled handoff.

Inspect After Relevant Events

Set inspection frequency and event triggers from the approved site plan and competent advice. Weather, water movement, nearby construction, impact, unauthorized access or movement may require an additional check. Record visible facts and escalate technical questions rather than diagnosing them.

Release to Installation

Before movement, compare current condition with the arrival baseline, confirm the current installation plan and identify every open exception. The delivery appointment plan and installation guide provide wider coordination context.

If a condition may affect a contractual claim, preserve evidence using the warranty evidence checklist. To request available product-side handling information, contact Rovellc with the order, unit, storage reason and planned duration.