FAT Action Handoff

Capsule house units illustrating factory acceptance action coordination

FAT Action Handoff

A capsule house factory acceptance test action handoff records observations, evidence, responsible parties, due dates and release gates after a buyer or project team reviews a unit before shipment. It prevents an open action from being mistaken for closure or shipment approval.

The purchase contract, approved specifications and authorized reviewers determine the required checks, acceptance criteria and release. This operational record does not replace engineering review, certification or contractual acceptance.

Fix the Test Reference

Record the purchase order, model or unit identifier, approved revision, review date, location, attendees and controlling procedure. Link photographs and records to the same unit and test step.

Build the Action Handoff

FieldRecordControl question
ObservationLocation, requirement and evidenceIs the issue traceable?
DispositionCorrect, clarify, accept or deferWho authorized it?
OwnerNamed organization and personWho supplies closure evidence?
Due gateDate and shipment dependencyDoes it block packing or release?
ClosureEvidence, reviewer and decisionWas closure recorded?

Separate Attendance from Acceptance

Attendance, test completion and document receipt do not automatically mean acceptance. Keep the unit or shipment at the applicable hold point until the designated reviewer records the required decision.

Close Actions Before Release

Retain the original observation, add correction evidence and record the reviewer response. If an item is deferred, identify the next control point and the party that carries the risk and action.

Use the pre-shipment inspection record for the wider buyer review and the supplier production status handoff for schedule coordination. Contact Rovellc for available product-side records within the agreed supply scope.